JPM: Data Center Infrastructure - 100 GW Pipeline and Counting

Key Points

  • AI datacenter pipeline totals ~110 GWs potential capacity, representing 5x+ current installed base
  • However, annual installs are true revenue driver; pipeline is ~45x the 2023 installation rate
  • Q2 2024 land deals related to potential 38 GWs in builds, with 1H building momentum continuing to accelerate
  • US Census data shows datacenter spending at only 2% of non-residential construction spending; manufacturing is 9x larger
  • V-shaped trajectory in datacenter spending accelerating through May 2024, supporting sequential increase in activity

Investment Implications

  • Timing prediction difficult but early evidence suggests sustained buildout acceleration
  • Datacenter spending share suggests room for continued expansion without overheating market
  • Annual build rate acceleration (not total capacity) drives revenue for equipment suppliers

Source

  • File: JPM-EE_MI_ Data Center Infrastructure_ Data Center Deep Dive Part 2_ AI 100 GW Pipeline_22Jul24.pdf
  • Location: Dropbox/2. Semi/Datacenter/
  • Pages: 21
  • Date: July 22, 2024
  • Analysts: C. Stephen Tusa Jr., Patrick M. Baumann, Chigusa Katoku, Chandreyee Sengupta